Here is an excerpt:
In the first week of above ground construction of Red Bull Arena, 872 pieces of steel (a total of 206 tons) have been set in place. The progress to date includes completion of the erection of structural steel and steel decking through Level 4 of the north half of the West building. This coming week, the steel columns and framing for Levels 5 and 6 are being set.